Floors: 12 above ground
Height: 46.63 m
Gross floor area: 18,058 m2
Completion: 05/2023
Status: under construction
Usage: hotel

Kennedyallee 87 Address

Kennedyallee 87
City: Frankfurt
District: Sachsenhausen

Location Rating

Score: 84 of 100
 
Powered by ViertelCheck

Kennedyallee 87 Rental

Phone: +49 69 173 269 391
Email: request via email

Involved Companies - Kennedyallee 87

Company Category
Eike Becker_Architekten architecture office

In Frankfurt’s Sachsenhausen district, a new residential tower with 12 floors is being built at Kennedyallee 87. At this prominent location, the top of the tall buildings triangle between Stresemannallee and Kennedyallee, three old office towers will be demolished by the end of 2018.

The design of the new residential tower comes from Eike Becker Architekten (Berlin), who are already well-known in the Greater Frankfurt Area, for example for the design of the future FAZ skyscraper at the Europaallee, for ma’ro (Goethequartier Neue Mainzer Strasse) and for the Vitopia Campus Kaiserlei.

On the ground floor, office space and/or commercial space will be constructed. From the second floor onwards a total amount of 181 serviced apartments will be constructed. The project developer is the Prime Group from Düsseldorf, Germany. All apartments will be equipped with a balcony. However, the loggias and balconies at the busy Kennedyallee will not be of much use.

The architecture design has much visual appeal, and above all, it will calm the currently jagged building front at Kennedyallee.

Frankfurt Rent Flat - Find Apartment in Frankfurt with skyline view - rent or buy housing - Mainhattan apartments

Rent or Buy an Apartment in Frankfurt?
Are you looking for an apartment or house with a skyline view, cheap or upscale, small or large? We know the best offers to rent or buy.

Planning and Construction

Kennedyallee - Hotel - Frankfurt - Neubau - Gleeds - KCM - Sachsenhausen
Kennedyallee-Aparthotel-Juli-2022

Status July 2022: The interior facade has been completed for about two weeks and the second floors are nearing completion. In two months, more than half of the interior work has already been completed. Furthermore, the roof technology has been completed. The next step is the installation of the representative facade area.

Prime Group Frankfurt - Highrise at Kennedyallee in Frankfurt, Germany - construction site as of September 2021
Frankfurt Cheval - Cheval Maison Frankfurt - Construction Site July 2021
Kennedyallee 87 Frankfurt - Cheval Collection Frankfurt - Cheval Mansion Frankfurt - construction site February 2021

Status May 2020: Cheval Collection from London becomes the operator of the apartments under the name Cheval Maison. The corresponding contract was signed with SIC Properties GmbH. Cheval Maison in Frankfurt is the first hotel of the British hotel operator in continental Europe. A roof garden with a view of the skyline should be a special feature. George Westwell, CEO of Cheval Collection, said: “This will be a flagship for us. Our second property outside of London and a milestone in our corporate goal of becoming the world leader in luxury apartments with service for any length of stay.

Status January 2020: A construction fence has been setup.

Condominium tower Frankfurt under construction Jan 2020

Status October 2019: The construction has not yet started.

Apartment tower at Kennedyallee Frankfurt - Design by Eike Becker Architekten

Status August 2018: The demolition work has begun and is carried out by AWR Abbruch.